Projects and work orders

A record of contracts, work orders and completion certificates for public departments, development agencies and private clients across Khyber Pakhtunkhwa.

Water supplyCompleted February 2024
Integrated Regional Support ProgrammeUNHCR

24 solarized water supply schemes in Afghan refugee villages

Client
Integrated Regional Support Programme (IRSP), supported by UNHCR
Scope
Solar powered water supply schemes across ten districts of Khyber Pakhtunkhwa
Status
Completion certificate issued 15 February 2024
Scheme locations
  • Koga, Buner
  • Batkhela, Malakand
  • Zangal Pattay, Malakand
  • Chakdara (two schemes), Lower Dir
  • Taimer, Lower Dir
  • Mayar, Lower Dir
  • Warai, Upper Dir
  • Dodba, Upper Dir
  • Kessu, Upper Dir
  • GK Khel, Bannu
  • Chechana, Kohat
  • Gamkol, Kohat
  • Khurasan, Peshawar
  • Badabera, Peshawar
  • Baghwaan, Peshawar
  • Ghandaf, Swabi
  • Barakai, Swabi
  • Baghicha, Mardan
  • Qutabghar, Mardan
  • Chitral
  • Munda, Charsadda
  • Utmanzai, Charsadda
  • Khazana, Charsadda
Water supplyTender IRSP/TENDER/2023/07/06
Integrated Regional Support Programme

Solarized water schemes with storage tanks and filtration plants

Client
Integrated Regional Support Programme (IRSP)
Contract
Signed 28 August 2023
Duration
1 September to 30 November 2023, 91 days
Districts
Buner, Charsadda, Haripur, Chitral, Lower Dir, Mardan, Peshawar, Swabi, Timergara and Upper Dir
Water supply
The Urban Unit

Groundwater recharge wells

Client
Urban Sector Planning and Management Services Unit (The Urban Unit), Lahore
Scope
Civil works for the construction of groundwater recharge wells
Water supply

Rainwater harvesting structure

Scope
Construction of a rainwater harvesting structure
Status
Completed, with completion certificate
Water supply
Government of Khyber Pakhtunkhwa

Irrigation works, District Swat

Client
Irrigation Department, Division Swat and Swat Irrigation Sub-Division
Scope
Completed irrigation works and supply of construction materials
Status
Completion and supply certificates issued
Bank branchesWork orders and completion certificates
Meezan Bank

Meezan Bank branch construction and renovation

New branch buildings, relocations and renovations delivered under the bank's own work orders. The new Mingora building was a complete construction over a three month programme, including completion of works left by a previous contractor.

  • New branch building, MingoraSwat
  • Mingora BranchSwat
  • Green ChowkMingora
  • Fawara ChowkSwat
  • Khwazakhela BranchNew branch, 2024
  • Sheikh Maltoon TownshipNew branch, Mardan
  • Parhoti BranchRelocation
  • Alpuri BranchShangla
  • SwabiSwabi
  • Main Bazar, ChakdaraLower Dir
  • Basharat MarketBranch works
  • Mardan BranchMardan
  • Barikot BranchSwat
  • Nowshera BranchNowshera
  • G.T. Road BranchPeshawar
  • Bannu BranchBannu
  • Bohar BazarBranch works
Roads and streetsAnnual Development Programme
Communication and Works Department, Khyber Pakhtunkhwa

Akhoon Baba Road

Scope
Construction of roads and bridges on a need basis, with reinforced cement pipe culverts and PCC road work
Roads and streetsADP No. 281/200195, 2020–21
Government of Khyber Pakhtunkhwa

Water supply, sanitation and PCC works, District Swat

Scope
Water supply, sanitation and plain cement concrete works across fourteen union councils
Sub-scheme
Sanitation and PCC at UC Barikot
Union councils
  • Shamozai
  • Parrai
  • Barikot
  • Kuz Aba Khel
  • Kota
  • Aboha
  • Ghalegay
  • Manyar
  • Gogdara
  • Tindodag
  • Odigram
  • Balogram
  • Qamber
  • Guligram
Roads and streetsProvincial ADP No. 667/190447
Government of Khyber Pakhtunkhwa

Streets and sanitation, UC Saidu Sharif

Programme
Malakand Area Development Programme
Scope
Pavement of streets and roads and a sanitation scheme at UC Saidu Sharif (PK-05)
Works
Tuff tiles, brick on edge paving and stone pitching
Roads and streetsDistrict Development Initiatives
Government of Khyber Pakhtunkhwa

Street pavement and drains, District Swat

Scope
Street pavement, roads, walls, drains and allied works
Packages
  • Tehsil Khwazakhela: street pavement and allied works
  • Tehsil Matta: street pavement, drains and allied works, including Package-1
  • UC Durashkhela: streets, roads, walls and drains, Package PK-09
Buildings and public works
Punjab Safe Cities Authority

Repair and maintenance of PSCA / PPIC3 buildings, Lot 3

Scope
Repair and maintenance of buildings under a formal contract with the employer
Signed by
Hazrat Rehman, Chief Executive Officer
Buildings and public worksIRSP
Integrated Regional Support Programme

Inclusive toilets, handwashing and incinerator works

Client
Integrated Regional Support Programme (IRSP), Mardan
Scope
New construction of inclusive toilets with handwashing facilities, an incinerator and related rehabilitation works
Duration
105 day construction period
Buildings and public worksADP No. 170064
Government of Khyber Pakhtunkhwa

Graveyard rehabilitation, Matta

Location
Tehsil Matta, District Swat
Scope
Boundary walls around existing graveyards
Sites
  • Kuza Durashkhela, Phase II
  • Shakar Dara, Phase III
  • Bazkhela

Copies of agreements, work orders and completion certificates are available to tender committees and clients on request.

Planning a similar project?

Tell us about the site, the scope and the timeline. The team will come back with a clear plan and an honest estimate.